01. |
Poor Concept |
 |
02. |
Poor Strategy or Concept |
 |
03. |
Judge by Only the Merit |
 |
04. |
Organizational Problems |
 |
05. |
Inflexible Management Structure |
 |
06. |
No Study at the First Failure |
 |
07. |
Misjudgment |
 |
08. |
Misjudgment of Situation |
 |
09. |
Planning and Design |
 |
10. |
Poor Planning |
 |
11. |
Poor Design |
 |
12. |
Non-Regular Movement |
 |
13. |
Movement During Transition |
 |
14. |
Thoughtless Phenomena |
 |
15. |
Secondary Damage |
 |
16. |
External Damage |
 |
17. |
Fire/Explosion |
 |
18. |
Bodily Harm |
 |
19. |
Death |
 |
20. |
2 person died |
 |
21. |
Bodily Harm |
 |
22. |
Injury |
 |
23. |
5 person injured |
 |
24. |
Loss to Organization |
 |
25. |
Economic Loss |
 |
26. |
Damage to Society |
 |
27. |
Change in Perception |
 |
28. |
Discredit to the Administration |
|
|
 |

Explosion and fire of a refuse derived fuel (RDF) storage tank
|
 |
Knowledge Comment: |
 |
If they had taken sufficient countermeasure at the trouble in early stage after the construction ?! |
|
|
|
|