Fire of powder resin due to increased powder by remodeling to improve efficiency at an ABS resin manufacturing plant
Case Details

Knowledge Comment:
You must not select something only by convinience. Confirm the safety.

Field Chemicals and Plants
Author WAKAKURA, Masahide (Kanagawa Industrial Technology Research Institute)
TAMURA, Masamitsu (Center for Risk Management and Safety Sciences, Yokohama National University)